6th June 2017

Progress report 6th June 2017

We are pleased to announce that the construction phase has now been completed. Commissioning is ongoing and should be completed by the end of July(2017)

The turbine has been running and making money since December 15th 2016. We are very pleased with the output so far even though the rainfall has been below average. The AGM is approaching soon and we hope to have some more details about returns for shareholders, final accounts of the project and income from the turbine so far. (All invoices are not yet processed but it looks promising to be at or better than we budgeted for)

Details of the forthcoming AGM will be published soon.