Great progress has been made over the last two weeks. The pipe has now crossed the forestry track and is connected and buried from the forebay tank at the reservoir down to within 15 meters of the turbine house. David Roberts has begun in earnest on the turbine house it is beginning to take shape. We expect to begin block work for the turbine house in the next 10 days. This is where the focus will be for the coming weeks.
CT Roberts and HGC have now left site and will return at the end of November or earlier December to connect the last 15 meters of pipe to the turbine house.